Lifecycle
Published Power BI page Issue Lifecycle & Overdue Monitoring, read on 13 October 2026. Overdue is an unresolved issue whose due date is before that day.
- Step
- 8
- Overdue
- 221
- As of
- 13 Oct 2026
- Source
- Issues
Source file Snowden Towers Sample Issue Summary.xlsx, ingested 2026-10-13T17:38:40+11:00. The published report is titled vis. Closed and Completed are resolved. Every other status is unresolved. The measures page counts 242 filled due dates and 47 blanks, and does not classify overdue.
Open Issue Lifecycle & Overdue Monitoring in Power BI
Cards
| Card | Reading |
|---|---|
| Overdue Issues | 221 |
| Unresolved Missing Due Date | 45 |
| Due Next 7 Days | — |
| Average Unresolved Age (Days) | 407.76 |
The four due groups add to 289. Due Next 7 Days is blank because no unresolved due date falls from 13 October 2026 through 20 October 2026. Average Unresolved Age is the mean of created-on age across the 267 unresolved issues, counted to 13 October 2026.
Due group
| Group | Issues | Share |
|---|---|---|
| Overdue | 221 | 76.47% |
| No due date | 45 | 15.57% |
| Resolved | 22 | 7.61% |
| Due later | 1 | — |
Resolved is Closed plus Completed, the same 22 as the overview resolution rate. The 47 blank due dates are 45 unresolved and 2 resolved. Due later is one issue, #1712, status In dispute, category Safety, due 14 January 2027. That slice is in the legend and is not labelled on the ring.
Overdue by status
Closed and Completed are absent. The seven counts add to 221.
| Status | Overdue |
|---|---|
| Open | 114 |
| In dispute | 50 |
| Draft | 37 |
| In progress | 7 |
| Not approved | 5 |
| Pending | 5 |
| In review | 3 |
Overdue by category
Safety, Concrete Crew, and Punch List are the three longest bars. Seven categories have one overdue issue. Life Safety - Design and XL Safety have none. The sixteen counts add to 221.
| Category | Overdue |
|---|---|
| Safety | 66 |
| Concrete Crew | 41 |
| Punch List | 39 |
| Admin Insurance | 20 |
| Observation | 14 |
| Commissioning | 12 |
| Design | 12 |
| Coordination | 5 |
| EPC Engineering Review | 5 |
| Change Management | 1 |
| Due Diligence | 1 |
| Earthwork | 1 |
| Fabrication | 1 |
| General | 1 |
| Installation | 1 |
| Quality | 1 |
The table under the charts lists id, title, status, due date, category, and created on. Row filters without a due date stay on the issues page.